Scheme Details
DISTRICT
Etawah
AGENCY
OMIL-JWIL (JV)
SCHEME ID
20099938
SCHEME NAME
NEVASAI
ESTIMATED COST
175.77
EXPENDITURE
108.26
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
13
Procured
13
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
10156.00
Meter
Length Laid
9950.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Etawah | Basrehar | Nivasai | 419770 | Nevasai | 205 | 193 | 94% | Work In Progress | Not Certified |