| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sitapur | NCC Ltd. | 20099950 | SUREPARA & DATOONI JJM SCHEME | 429.89 | 194.29 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 25 | 25 | Yes | 0 | NA | No | 16386.00 | 15500.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Behta | Datooni | 410805 | Datooni | 198 | 197 | 99 | Work In Progress | Not Certified |
| 2 | Sitapur | Behta | Surepara | 410852 | Godhia | 78 | 70 | 90 | Work In Progress | Not Certified |
| 3 | Sitapur | Behta | Surepara | 410853 | Saure Para | 180 | 178 | 99 | Work In Progress | Not Certified |
| 4 | Sitapur | Behta | Surepara | 410854 | Sikrohar Kala | 111 | 100 | 90 | Work In Progress | Not Certified |
| 5 | Sitapur | Behta | Sohariya | 410855 | JAITPUR | 1 | 0 | 0 | Work In Progress | Not Certified |