Scheme Details
DISTRICT
Gorakhpur
AGENCY
Rithwik-Koya (JV)
SCHEME ID
20099985
SCHEME NAME
PIPRA BUZURG JJM
ESTIMATED COST
219.80
EXPENDITURE
91.50
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
10032.00
Meter
Length Laid
10029.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Uruwa | Pipari Bujurg | 456020 | Pipari Bujurg | 146 | 146 | 100% | Har Ghar Jal | Not Certified |
| 2 | Gorakhpur | Uruwa | Pipari Bujurg | 456021 | Rautpar Bujurg | 120 | 115 | 96% | Work In Progress | Not Certified |
| 3 | Gorakhpur | Uruwa | Pipari Bujurg | 456022 | Marar | 49 | 21 | 43% | Work In Progress | Not Certified |
| 4 | Gorakhpur | Uruwa | Pipari Bujurg | 456023 | Goura | 13 | 1 | 8% | Work In Progress | Not Certified |
| 5 | Gorakhpur | Uruwa | Pipari Bujurg | 456024 | Pipari Khurd | 28 | 1 | 4% | Work In Progress | Not Certified |