Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Vindhya-GAJA (JV) | 20100184 | MUBARAKPUR TAPPA BA &ASFABAD BHAWAN BA WSS | 361.78 | 63.66 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 30 | 0 | NA | 0 | NA | No | 7536.00 | 5616.50 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Alhepur | Asfabad Bhavan Bila Ahatmali | 387143 | Asfabad Bhavan Bila Ahatmali | 240 | 210 | 88 | Work In Progress | Not Certified |
| 2 | Bijnor | Alhepur | Mubarakpur Tappa Ahatmali | 387144 | Mubarakpur Tappa Ahatmali | 255 | 213 | 84 | Work In Progress | Not Certified |
| 3 | Bijnor | Alhepur | Mubarakpur Tappa Ahatmali | 387145 | Laidarpur | 139 | 139 | 100 | Har Gar Jal | Not Certified |