Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Larsen & Toubro Ltd | 20100277 | HILALPUR JJM SCHEME | 178.56 | 121.09 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 11 | 11 | Yes | 0 | NA | No | 5574.00 | 5574.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Laharpur | Hilalpur | 410662 | Bankat | 70 | 70 | 100 | Har Gar Jal | Not Certified |
| 2 | Sitapur | Laharpur | Hilalpur | 410665 | Hatiya Upree | 47 | 47 | 100 | Har Gar Jal | Certified |
| 3 | Sitapur | Laharpur | Hilalpur | 410666 | Hilalpur Khueuru | 92 | 92 | 100 | Har Gar Jal | Certified |