Scheme Details
DISTRICT
Bulandshahr
AGENCY
Power Mech Projects Ltd
SCHEME ID
20100301
SCHEME NAME
Sarai Chhabila Reorganisation WSS
ESTIMATED COST
457.46
EXPENDITURE
238.56
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
44
Procured
44
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
17407.00
Meter
Length Laid
13000.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bulandshahr | Lakhaothi | Sarai Chhabila | 393358 | Sarai Chhabila | 1247 | 1247 | 100% | Har Ghar Jal | Not Certified |