Scheme Details
DISTRICT
Bulandshahr
AGENCY
Power Mech Projects Ltd
SCHEME ID
20100309
SCHEME NAME
Saidpur Reorganisation WSS
ESTIMATED COST
715.85
EXPENDITURE
440.63
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
44
Procured
44
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
32022.00
Meter
Length Laid
31000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bulandshahr | Bhawan Bahadur Nagar | Saidpur | 393206 | Mahuddinpur | 77 | 35 | 45% | Work In Progress | Not Certified |
| 2 | Bulandshahr | Bhawan Bahadur Nagar | Saidpur | 393207 | Darveshpur | 6 | 2 | 33% | Work In Progress | Not Certified |
| 3 | Bulandshahr | Bhawan Bahadur Nagar | Saidpur | 393210 | Modh.allipur Urf Nima Patty | 143 | 136 | 95% | Work In Progress | Not Certified |
| 4 | Bulandshahr | Bhawan Bahadur Nagar | Saidpur | 393211 | Saidpur | 1260 | 322 | 26% | Work In Progress | Not Certified |