Scheme Details
DISTRICT Bulandshahr
AGENCY Power Mech Projects Ltd
SCHEME ID 20100309
SCHEME NAME Saidpur Reorganisation WSS
ESTIMATED COST 715.85
EXPENDITURE 440.63
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 1
Solar Plant
Required 44
Procured 44 KW
Work Status No
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 32022.00 Meter
Length Laid 31000.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Bulandshahr Bhawan Bahadur Nagar Saidpur 393206 Mahuddinpur 77 35 45% Work In Progress Not Certified
2 Bulandshahr Bhawan Bahadur Nagar Saidpur 393207 Darveshpur 6 2 33% Work In Progress Not Certified
3 Bulandshahr Bhawan Bahadur Nagar Saidpur 393210 Modh.allipur Urf Nima Patty 143 136 95% Work In Progress Not Certified
4 Bulandshahr Bhawan Bahadur Nagar Saidpur 393211 Saidpur 1260 322 26% Work In Progress Not Certified