Scheme Details
DISTRICT
Bulandshahr
AGENCY
Power Mech Projects Ltd
SCHEME ID
20100312
SCHEME NAME
Akbarpur WSS
ESTIMATED COST
571.81
EXPENDITURE
286.72
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
25
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
22171.00
Meter
Length Laid
50000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bulandshahr | Bulandshahr | Kamalpur | 393408 | Kamalpur | 531 | 531 | 100% | Har Ghar Jal | Not Certified |
| 2 | Bulandshahr | Bulandshahr | Akbarpur | 393409 | Akbarpur | 940 | 940 | 100% | Har Ghar Jal | Not Certified |