Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Larsen & Toubro Ltd | 20100330 | GAGAWR WATER SUPPLY SCHEME | 240.68 | 40.11 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 0 | 0 | 1 | 1 | 0 | 0 | 0 | NA | 0 | NA | No | 0.00 | 0.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Phulpur | Gagawr | 432319 | Gagawr | 210 | 202 | 96 | Work In Progress | Not Certified |
| 2 | Prayagraj | Phulpur | Gagawr | 432320 | Atamadpur Urf Mishrapur | 191 | 180 | 94 | Work In Progress | Not Certified |