Scheme Details
DISTRICT
Ghazipur
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20100573
SCHEME NAME
KHUTHAN W/S SCHEME
ESTIMATED COST
285.80
EXPENDITURE
82.87
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
15
Procured
15
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12109.00
Meter
Length Laid
12109.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Manihari | Kuthan | 471770 | Kuthan | 266 | 266 | 100% | Har Ghar Jal | Not Certified |