Scheme Details
DISTRICT
Azamgarh
AGENCY
M/s Sudhakara Infratech Pvt. Ltd
SCHEME ID
20100588
SCHEME NAME
VIJAIYAPAR WATER SUPPLY
ESTIMATED COST
387.36
EXPENDITURE
177.74
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
37
Procured
37
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9012.00
Meter
Length Laid
8712.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Bilariaganj | Vijayapar | 462067 | Vijayapar | 205 | 200 | 98% | Work In Progress | Not Certified |
| 2 | Azamgarh | Bilariaganj | Vijayapar | 462068 | Maduapar | 60 | 56 | 93% | Work In Progress | Not Certified |