Scheme Details
DISTRICT Gonda
AGENCY KLSR - RAYS (JV)
SCHEME ID 20100619
SCHEME NAME BARDAHA & BARTARA WSS
ESTIMATED COST 284.88
EXPENDITURE 180.25
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 0
Solar Plant
Required 20
Procured 20 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 18344.00 Meter
Length Laid 17326.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Gonda Colonelganj BARTARA 445382 BARTARA 144 132 92% Work In Progress Not Certified
2 Gonda Colonelganj BARDAHA 445383 RAMPUR 99 83 84% Work In Progress Not Certified