Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Gonda | Larsen & Toubro Ltd | 20100627 | Changeriya -Budhwaliya Water Supply Scheme | 485.11 | 0.00 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 0 | 0 | 0 | 1 | 0 | 0 | 10 | 10 | Yes | 0 | NA | No | 25542.00 | 25542.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gonda | Colonelganj | Changeriya | 445326 | Changeriya | 511 | 467 | 91 | Work In Progress | Not Certified |
| 2 | Gonda | Colonelganj | Budhwaliya | 445327 | Budhwaliya | 462 | 397 | 86 | Work In Progress | Not Certified |