Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Kanpur Nagar | Vindhya-GAJA (JV) | 20100855 | PARGAHI BANGAR & HORA KACHHAR GRAM PANCHAYAT WATER SUPPLY SCHEME | 398.86 | 285.65 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Kanpur Nagar | Kalyanpur | Hora Kachhar | 422270 | Hora Kachhar | 234 | 234 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Kanpur Nagar | Kalyanpur | Hora Kachhar | 422271 | Gangpur Kachhar | 21 | 21 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Kanpur Nagar | Kalyanpur | Hora Kachhar | 422272 | Naramaukachhar | 143 | 143 | 100 | Har Gar Jal | Not Certified | Not Verified |
4 | Kanpur Nagar | Kalyanpur | Pargahi Bangar | 422274 | Pargahi Bangar | 197 | 197 | 100 | Har Gar Jal | Not Certified | Not Verified |
5 | Kanpur Nagar | Kalyanpur | Pargahi Bangar | 422275 | Bagdodhikachhar&pargahi Kachha | 267 | 267 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 44 | 44 | Yes | 0 | NA | No | 18786.00 | 18766.00 |