Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Bijnor
AGENCY LC INFRA
SCHEME ID 20100872
SCHEME NAME Raipur Malihabad WSS
ESTIMATED COST 134.90
EXPENDITURE 127.84
AUTOMATION STATUS
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 1
Solar Plant
Required 9
Procured 9 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 4310.00 Meter
Length Laid 5000.00 Meter

Scheme Assigned Villages

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Bijnor Netaur Raipur Mahilabad 386873 Raipur Malihabad 99 99 100% Har Ghar Jal Certified
2 Bijnor Netaur Raipur Mahilabad 386874 Bharakheri Urf Dugri 51 51 100% Har Ghar Jal Certified
3 Bijnor Netaur Raipur Mahilabad 678049 Mamurpur Gazi 92 92 100% Har Ghar Jal Certified