Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Mau | GA INFRA-VPL | 20100919 | BANGANWA GRAM PANCHAYAT WATER SUPPLY SCHEME | 265.44 | 78.07 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 0 | 0 | 0 | 1 | 0 | 0 | 18 | 18 | NA | 0 | NA | No | 14419.00 | 8000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Badraon | Banganwa | 465242 | Banganwa | 177 | 177 | 100 | Har Gar Jal | Not Certified |
| 2 | Mau | Badraon | Banganwa | 465243 | Manikpur Hadahwa | 131 | 131 | 100 | Har Gar Jal | Not Certified |