Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Kasganj | PNC-SPML-JV | 20100988 | KUTUB PUR SARAI | 391.97 | 109.93 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 37 | 37 | Yes | 0 | NA | No | 21049.00 | 21049.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kasganj | Patiyali | Kutub Pur Sarai | 398988 | Kutub Pur Sarai | 591 | 585 | 99 | Work In Progress | Not Certified |
| 2 | Kasganj | Patiyali | Kutub Pur Sarai | 398989 | Raipur Mothar | 74 | 73 | 99 | Work In Progress | Not Certified |
| 3 | Kasganj | Patiyali | Kutub Pur Sarai | 398990 | Visvnodi | 102 | 98 | 96 | Work In Progress | Not Certified |