| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Budaun | PNC-SPML-JV | 20101041 | mohammadpur udha water supply scheme | 165.60 | 68.55 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 13 | 13 | Yes | 0 | NA | No | 3460.00 | 3000.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Budaun | Sahaswan | Mohammadpur Udha | 401596 | Mohammadpur Uda | 135 | 135 | 100 | Har Gar Jal | Not Certified | 
| 2 | Budaun | Sahaswan | Mohammadpur Udha | 401601 | Manakpur | 80 | 80 | 100 | Har Gar Jal | Not Certified |