Scheme Details
DISTRICT
Bulandshahr
AGENCY
JMC - Lakshmi (JV)
SCHEME ID
20101067
SCHEME NAME
Amarnath Babu Urf Unchagaon Khadar WSS
ESTIMATED COST
199.67
EXPENDITURE
101.77
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
7388.00
Meter
Length Laid
6986.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bulandshahr | Dibai | AMARNATH BABU URF UNCHAGAON KHADAR | 393866 | AMARNA BABU/UNCHA GAON KHADER | 264 | 255 | 97% | Work In Progress | Not Certified |