Scheme Details
DISTRICT
Fatehpur
AGENCY
Gayatri Projects LTD
SCHEME ID
20101123
SCHEME NAME
Kashmiri Pur
ESTIMATED COST
216.49
EXPENDITURE
40.40
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
22
Procured
22
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
7891.00
Meter
Length Laid
7885.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Devmai | Kashmiri Pur | 427333 | Kashmiripur | 337 | 177 | 53% | Work In Progress | Not Certified |