Scheme Details
DISTRICT Aligarh
AGENCY JMC - Lakshmi (JV)
SCHEME ID 20101141
SCHEME NAME Faridpur wss
ESTIMATED COST 159.81
EXPENDITURE 13.45
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 16
Procured 16 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 1822.00 Meter
Length Laid 1810.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Aligarh Jawan TATARGARHI FARIDPUR 394652 FARIDPUR 116 88 76% Work In Progress Not Certified
2 Aligarh Jawan FARIDPUR 394676 FARIDPUR 319 0 0% Work In Progress Not Certified