Scheme Details
DISTRICT
Budaun
AGENCY
PNC-SPML-JV
SCHEME ID
20101195
SCHEME NAME
kunwarpur water supply scheme
ESTIMATED COST
143.48
EXPENDITURE
61.30
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
25
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
4385.00
Meter
Length Laid
4385.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Budaun | Islamnagar | Kunwarpur | 401204 | Kunwarpur | 205 | 200 | 98% | Work In Progress | Not Certified |