Scheme Details
DISTRICT
Bijnor
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20101221
SCHEME NAME
Noorpur Arab WSS
ESTIMATED COST
291.25
EXPENDITURE
243.60
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
27
Procured
27
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6955.00
Meter
Length Laid
6283.52
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Kotwali | Noorpur Arab | 386364 | Noorpur Arab | 399 | 399 | 100% | Har Ghar Jal | Not Certified |
| 2 | Bijnor | Kotwali | Noorpur Arab | 386365 | Mohammadpur Garhi | 5 | 1 | 20% | Work In Progress | Not Certified |