Scheme Details
DISTRICT
Budaun
AGENCY
PNC-SPML-JV
SCHEME ID
20101245
SCHEME NAME
NUDDHA NAGAR WATER SUPPLY SCHEME
ESTIMATED COST
137.66
EXPENDITURE
67.43
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
25
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6855.00
Meter
Length Laid
6855.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Budaun | Islamnagar | Buddha Nagar | 401264 | Buddha Nagar | 114 | 113 | 99% | Work In Progress | Not Certified |
| 2 | Budaun | Islamnagar | Buddha Nagar | 401265 | Chhibau Khurd | 63 | 61 | 97% | Work In Progress | Not Certified |