Scheme Details
DISTRICT
Azamgarh
AGENCY
SIEPL – BRCCPL (JV) / SKYLARK
SCHEME ID
20101262
SCHEME NAME
Pankarpur WATER SUPPLY SCHEME
ESTIMATED COST
174.23
EXPENDITURE
88.52
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
13
Procured
13
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
8954.00
Meter
Length Laid
8954.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Ahiraula | Pankarpur | 461461 | Shahpur | 60 | 50 | 83% | Work In Progress | Not Certified |
| 2 | Azamgarh | Ahiraula | Pankarpur | 461463 | Pankarpur | 74 | 73 | 99% | Work In Progress | Not Certified |
| 3 | Azamgarh | Ahiraula | Pankarpur | 461464 | Kathai Chover | 4 | 1 | 25% | Work In Progress | Not Certified |