Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Moradabad
AGENCY LC INFRA
SCHEME ID 20101298
SCHEME NAME Sarkara Karim (mst) Village Water Supply Scheme
ESTIMATED COST 291.55
EXPENDITURE 145.36
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 27
Procured 27 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 7577.00 Meter
Length Laid 6300.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Moradabad Dilari Sarkara Karim (m.s.t) 387843 Sarkara Karim (m.s.t) 648 646 100% Work In Progress Not Certified
2 Moradabad Dilari Sarakara Khas 387852 Sarakara Khas 426 426 100% Har Ghar Jal Not Certified