Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Budaun
AGENCY PNC-SPML-JV
SCHEME ID 20101379
SCHEME NAME DAULATPUR WATER SUPPLY SCHEME
ESTIMATED COST 164.86
EXPENDITURE 132.26
AUTOMATION STATUS
Disconnected View Live Screen
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 13
Procured 13 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 3193.00 Meter
Length Laid 3193.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Budaun Asafpur Daulatpur 401109 Daulatpur 262 262 100% Har Ghar Jal Certified