Scheme Details
DISTRICT Gonda
AGENCY Larsen & Toubro Ltd
SCHEME ID 20101407
SCHEME NAME Nandaur 1 & 2 Water supply scheme
ESTIMATED COST 455.32
EXPENDITURE 194.66
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 2
Boring Done 2
Air Compressor Done 2
O.P. Unit Done 2
OHT Progress
Required 2
Work Started 0
Work Completed 0
Solar Plant
Required 18
Procured 17 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 42271.00 Meter
Length Laid 0.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Gonda Paraspur Nandaur 445463 Nandaur 785 775 99% Work In Progress Not Certified