Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Siddharth Nagar
AGENCY JAKSON - VISHVARAJ (JV)
SCHEME ID 20101448
SCHEME NAME Jharuya G.O.V WSS
ESTIMATED COST 340.10
EXPENDITURE 139.63
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 5
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 23
Procured 23 KW
Work Status NA
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 22228.00 Meter
Length Laid 22200.00 Meter

Scheme Assigned Villages

5 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Siddharth Nagar Barhni Halaura 446411 Halaura 133 95 71% Work In Progress Not Certified
2 Siddharth Nagar Barhni Halaura 446412 Golhaura Ahatmali 31 20 65% Work In Progress Not Certified
3 Siddharth Nagar Barhni Jharuva 446420 Jharuya 198 87 44% Work In Progress Not Certified
4 Siddharth Nagar Barhni Jharuva 446421 Kamhariya 68 14 21% Work In Progress Not Certified
5 Siddharth Nagar Barhni Jharuva 446422 Bhelauji 42 35 83% Work In Progress Not Certified