Scheme Details
DISTRICT
Deoria
AGENCY
LC INFRA
SCHEME ID
20101549
SCHEME NAME
JOGIYA GP BHALUANI BLOCK WATER SUPPLY SCHEME
ESTIMATED COST
302.32
EXPENDITURE
123.82
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
23
Procured
23
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9233.00
Meter
Length Laid
3000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Deoria | Bhaluani | Jogiya | 459928 | Pidra | 51 | 47 | 92% | Work In Progress | Not Certified |
| 2 | Deoria | Bhaluani | Jogiya | 459929 | Mundera | 116 | 108 | 93% | Work In Progress | Not Certified |
| 3 | Deoria | Bhaluani | Jogiya | 459930 | Jogdiha | 39 | 29 | 74% | Work In Progress | Not Certified |
| 4 | Deoria | Bhaluani | Jogiya | 459931 | Jogiya | 78 | 70 | 90% | Work In Progress | Not Certified |
| 5 | Deoria | Bhaluani | Jogiya | 459932 | Hardeora | 62 | 57 | 92% | Work In Progress | Not Certified |