Scheme Details
DISTRICT Shahjahanpur
AGENCY NCC Ltd.
SCHEME ID 20101596
SCHEME NAME DOSHPUR THOK GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST 226.81
EXPENDITURE 121.09
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 15
Procured 15 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 5684.00 Meter
Length Laid 5669.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Shahjahanpur Mirzapur Doshpur Thok 407583 Doshpur Thok 353 347 98% Work In Progress Not Certified
2 Shahjahanpur Mirzapur Doshpur Nagar 407601 Doshpur Nagar 480 480 100% Har Ghar Jal Not Certified