Scheme Details
DISTRICT Sitapur
AGENCY Larsen & Toubro Ltd
SCHEME ID 20101623
SCHEME NAME GAURA JJM SCHEME
ESTIMATED COST 319.02
EXPENDITURE 205.51
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 18
Procured 18 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 8419.00 Meter
Length Laid 8419.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Sitapur Ealliya Gaura 410197 Gaura 210 207 99% Work In Progress Not Certified
2 Sitapur Ealliya Gaura 410198 Ojhipur 21 15 71% Work In Progress Not Certified
3 Sitapur Ealliya Gaura 410199 Pratappur 146 111 76% Work In Progress Not Certified
4 Sitapur Ealliya Gaura 410200 Sarrayan 165 160 97% Work In Progress Not Certified