Scheme Details
DISTRICT
Bijnor
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20101803
SCHEME NAME
RAMJIWALA WSS
ESTIMATED COST
294.13
EXPENDITURE
230.23
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
7
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
14127.00
Meter
Length Laid
13424.50
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
7 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Kotwali | Ramjiwala | 386372 | Rampur | 7 | 1 | 14% | Work In Progress | Not Certified |
| 2 | Bijnor | Kotwali | Ramjiwala | 386376 | Chapra | 41 | 24 | 59% | Work In Progress | Not Certified |
| 3 | Bijnor | Kotwali | Ramjiwala | 386380 | CHAKMIA MOHKAMSINGH | 3 | 1 | 33% | Work In Progress | Not Certified |
| 4 | Bijnor | Kotwali | Ramjiwala | 693733 | KUSHALWALA | 181 | 181 | 100% | Har Ghar Jal | Not Certified |
| 5 | Bijnor | Kotwali | Ramjiwala | 693739 | ASADULLAPUR | 15 | 1 | 7% | Work In Progress | Not Certified |
| 6 | Bijnor | Kotwali | Ramjiwala | 694165 | DHAKARIYA | 3 | 1 | 33% | Work In Progress | Not Certified |
| 7 | Bijnor | Kotwali | Ramjiwala | 694166 | DISAUNDIWALA JANGAL | 8 | 1 | 12% | Work In Progress | Not Certified |