Scheme Details
DISTRICT
Auraiya
AGENCY
GVPR
SCHEME ID
20101891
SCHEME NAME
Mau(khidarpur)PWS
ESTIMATED COST
95.46
EXPENDITURE
87.96
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
0
Work Started
0
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
25
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
2820.00
Meter
Length Laid
2820.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Auraiya | Bidhuna | Mau | 420280 | Narayanpur Shar | 40 | 1 | 2% | Work In Progress | Not Certified |
| 2 | Auraiya | Bidhuna | Mau | 420281 | Khidarpur | 41 | 1 | 2% | Work In Progress | Not Certified |