Scheme Details
DISTRICT
Gonda
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20101955
SCHEME NAME
DHAMSARA GP WSS
ESTIMATED COST
150.16
EXPENDITURE
74.47
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
8
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6792.00
Meter
Length Laid
6700.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gonda | Haldharmau | DHAMSARA | 445192 | DHAMSARA | 179 | 167 | 93% | Work In Progress | Not Certified |