Scheme Details
DISTRICT
Fatehpur
AGENCY
Power Mech Projects Ltd
SCHEME ID
20102047
SCHEME NAME
ADAWAL RO
ESTIMATED COST
284.13
EXPENDITURE
218.33
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
13
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
8877.00
Meter
Length Laid
8859.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Asother | Adawal | 428133 | Adawal | 824 | 630 | 76% | Work In Progress | Not Certified |