DISTRICT Ghaziabad
AGENCY LC INFRA
SCHEME ID 20102070
SCHEME NAME JAHALAWA AND ASADPUR NAGAL (MVS) VILLAGE WATER SUPPLY SCHEME
ESTIMATED COST 350.14
EXPENDITURE 233.84
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 27
Procured 27 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 10223.00 Meter
Length Laid 10813.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Ghaziabad Muradnagar Asadpur Nagal 392192 Arsadpur Nagal 373 366 98% Work In Progress Not Certified
2 Ghaziabad Muradnagar Jhalawa 392193 Jahalawa 449 449 100% Har Ghar Jal Not Certified