Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Mau
AGENCY KLSR - RAYS (JV)
SCHEME ID 20102330
SCHEME NAME Atrari Water supply scheme
ESTIMATED COST 490.94
EXPENDITURE 255.45
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 2
Boring Done 2
Air Compressor Done 2
O.P. Unit Done 2
OHT Progress
Required 1
Work Started 0
Work Completed 1
Solar Plant
Required 44
Procured 44 KW
Work Status No
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 19631.00 Meter
Length Laid 16922.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Mau Muhammadabad Gohana Atrari 465937 Atrari 1108 1096 99% Work In Progress Not Certified
2 Mau Muhammadabad Gohana Atrari 465938 Dhaurahara 93 79 85% Work In Progress Not Certified
3 Mau Muhammadabad Gohana Atrari 678165 Salahabad 3 1 33% Work In Progress Not Certified