Scheme Details
DISTRICT
Azamgarh
AGENCY
M/s Sudhakara Infratech Pvt. Ltd
SCHEME ID
20102339
SCHEME NAME
Rasulpur water supply scheme
ESTIMATED COST
247.84
EXPENDITURE
142.63
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
23
Procured
23
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
7409.00
Meter
Length Laid
6275.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Mirzapur | RASULPUR BAISAR | 463449 | Rasulpur | 474 | 473 | 100% | Work In Progress | Not Certified |