Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Azamgarh
AGENCY M/s Sudhakara Infratech Pvt. Ltd
SCHEME ID 20102340
SCHEME NAME KADIPUR HARIKESH Water supply scheme
ESTIMATED COST 175.18
EXPENDITURE 118.29
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 16
Procured 16 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 3857.00 Meter
Length Laid 3675.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Azamgarh Bilariaganj Kadipur Harkesh 462017 Kadipur Harikesh 193 188 97% Work In Progress Not Certified