Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | JAKSON - VISHVARAJ (JV) | 20102424 | MAJHAUWA CHAUBEY GP wss (J) | 282.88 | 110.22 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 20 | 20 | Yes | 0 | NA | No | 11063.00 | 10000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Gaur | Majhauwa Chaubey | 449575 | Majhauwa Chaubey | 191 | 190 | 99 | Work In Progress | Not Certified |
| 2 | Basti | Gaur | Majhauwa Chaubey | 449576 | Aganiya Pur | 21 | 21 | 100 | Har Gar Jal | Not Certified |
| 3 | Basti | Gaur | Majhauwa Chaubey | 449577 | Sari Deen Dayal | 52 | 35 | 67 | Work In Progress | Not Certified |
| 4 | Basti | Gaur | Majhauwa Chaubey | 449578 | Madhawa Pur | 46 | 41 | 89 | Work In Progress | Not Certified |
| 5 | Basti | Gaur | Majhauwa Chaubey | 449579 | Tenuwa | 106 | 101 | 95 | Work In Progress | Not Certified |