Scheme Details
DISTRICT
Bijnor
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20102453
SCHEME NAME
GUNIAKHERI WSS
ESTIMATED COST
217.90
EXPENDITURE
131.88
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
20
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
3525.00
Meter
Length Laid
3171.21
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Noorpur | Guniakheri | 387662 | Guniakheri | 284 | 284 | 100% | Har Ghar Jal | Not Certified |
| 2 | Bijnor | Noorpur | Guniakheri | 387664 | Sidi1awali | 174 | 174 | 100% | Har Ghar Jal | Not Certified |