Scheme Details
DISTRICT
Chandauli
AGENCY
GA INFRA - BABA (JV)
SCHEME ID
20102779
SCHEME NAME
Nadesar_Marufpur WS
ESTIMATED COST
565.70
EXPENDITURE
191.42
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
6
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
39
Procured
39
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
27592.00
Meter
Length Laid
16801.00
Meter
Scheme Assigned Villages
6 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Chandauli | Chahaniya | Marufpur | 474094 | Marufpur | 451 | 451 | 100% | Har Ghar Jal | Certified |
| 2 | Chandauli | Chahaniya | Marufpur | 474095 | Chak Bulan | 19 | 19 | 100% | Har Ghar Jal | Certified |
| 3 | Chandauli | Chahaniya | Marufpur | 474096 | Shahbajpur | 22 | 22 | 100% | Har Ghar Jal | Certified |
| 4 | Chandauli | Chahaniya | Nadesar | 474097 | Nadesar | 341 | 341 | 100% | Har Ghar Jal | Certified |
| 5 | Chandauli | Chahaniya | Marufpur | 656985 | Mustafapur | 44 | 44 | 100% | Har Ghar Jal | Not Certified |
| 6 | Chandauli | Chahaniya | Nadesar | 656986 | Salempur | 34 | 34 | 100% | Har Ghar Jal | Not Certified |