Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Vindhya-GAJA (JV) | 20106694 | SULEMAN SHIKHOPUR GOV WSS | 838.00 | 274.93 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 8 | 4 | 4 | 4 | 4 | 1 | 0 | 1 | 68 | 16 | Yes | 0 | NA | No | 53837.00 | 45570.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Kotwali | Sulema Shikohpur | 386329 | Sulema Shikohpur | 42 | 6 | 14 | Work In Progress | Not Certified |
| 2 | Bijnor | Kotwali | Sulema Shikohpur | 386330 | Rajpur Kot | 1 | 1 | 100 | Har Gar Jal | Not Certified |
| 3 | Bijnor | Kotwali | Sulema Shikohpur | 386333 | Murtajabad | 14 | 1 | 7 | Work In Progress | Not Certified |
| 4 | Bijnor | Kotwali | Sulema Shikohpur | 386334 | Shankerpur | 12 | 1 | 8 | Work In Progress | Not Certified |
| 5 | Bijnor | Kotwali | Sulema Shikohpur | 386335 | Nathewali | 59 | 1 | 2 | Work In Progress | Not Certified |
| 6 | Bijnor | Kotwali | Sulema Shikohpur | 386336 | Haloowali | 128 | 121 | 95 | Work In Progress | Not Certified |
| 7 | Bijnor | Kotwali | Sulema Shikohpur | 386337 | Khokra | 3 | 1 | 33 | Work In Progress | Not Certified |
| 8 | Bijnor | Kotwali | Sulema Shikohpur | 700117 | QADARGANJ | 67 | 52 | 78 | Work In Progress | Not Certified |