Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Basti JAKSON - VISHVARAJ (JV) 20106704 SHAU DEEH & BADHARNI GP wss (J) 442.08 124.41 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
2 1 1 1 1 1 0 0 27 27 Yes 0 NA No 21087.00 21000.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Basti Gaur Badharni 449404 Badharni 188 188 100 Har Gar Jal Not Certified
2 Basti Gaur Shau Deeh 449408 Shau Deeh 505 505 100 Har Gar Jal Not Certified