Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Farrukhabad | Vindhya-GAJA (JV) | 20111034 | Reorginisation of Dhilawal wss | 1078.76 | 386.01 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 5 | 5 | 5 | 5 | 2 | 0 | 2 | 0 | 0 | NA | 68 | NA | No | 42787.00 | 39782.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Farrukhabad | Barahpur | Dhilawal | 418479 | Dhilawal | 1020 | 1016 | 100 | Work In Progress | Not Certified | 
| 2 | Farrukhabad | Barahpur | Bhau Pur Khurd | 418485 | Bhau Pur Khurd | 573 | 428 | 75 | Work In Progress | Not Certified | 
| 3 | Farrukhabad | Barahpur | Papiha Pur | 418487 | Papiha Pur | 948 | 709 | 75 | Work In Progress | Not Certified | 
| 4 | Farrukhabad | Barahpur | Bijadhar Pur/bijadhar Pur Central Jail | 418488 | Bijadhar Pur/bijadhar Pur Central Jail | 358 | 348 | 97 | Work In Progress | Not Certified |