Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Sitapur | NCC Ltd. | 20126334 | Paidapur water supply scheme | 245.26 | 0.00 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | NA | No | 0.00 | 300.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Machrehta | Paidapur | 410007 | Bhaupur | 102 | 102 | 100 | Har Gar Jal | Not Certified | 
| 2 | Sitapur | Machrehta | Paidapur | 410008 | Padari | 50 | 50 | 100 | Har Gar Jal | Not Certified | 
| 3 | Sitapur | Machrehta | Paidapur | 410009 | Paidapur | 254 | 242 | 95 | Work In Progress | Not Certified |