Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Deoria | Gayatri Projects LTD | 7372173 | Ghuri Kund Khurd PWS Scheme 2015 16 | 195.04 | 194.70 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Deoria | Pathardewa | KABILASAWA KHURD | 459118 | KABILASAWA KHURD | 263 | 263 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Deoria | Rudrapur | Bhabhauli | 459783 | Majhauli | 170 | 170 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Deoria | Rudrapur | Bhabhauli | 459784 | Sarya | 32 | 29 | 91 | Work In Progress | Not Certified | Not Verified |
4 | Deoria | Rudrapur | Bhabhauli | 459785 | Gopalpur | 143 | 142 | 99 | Work In Progress | Not Certified | Not Verified |
5 | Deoria | Rudrapur | Ramaipura | 459794 | Ramaipura | 182 | 178 | 98 | Work In Progress | Not Certified | Not Verified |
6 | Deoria | Rudrapur | Ramaipura | 459795 | Malpatti | 93 | 86 | 92 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
6 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | NA | 0 | NA | No | 9438.00 | 9000.00 |