Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Approve By Agency Status Approve By EE Status Automation Status
1 Lalitpur DARA ENGINEERING 8136187 Badanpur GOV 8836.00 7608.96 Verified Verified view more

Scheme Assigne Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified Handed Over Villages
1 Lalitpur Talbehat Baghaura 424504 Baghaura 228 228 100 Har Gar Jal Certified Not Verified
2 Lalitpur Talbehat Baghaura 424505 Naya Khera 73 73 100 Har Gar Jal Certified Not Verified
3 Lalitpur Talbehat Baghaura 424507 Hajariya 101 101 100 Har Gar Jal Certified Not Verified
4 Lalitpur Talbehat Pura Kalan 424531 Didora 63 63 100 Har Gar Jal Certified Verified
5 Lalitpur Talbehat Sarsen 424536 Sarsen 193 193 100 Har Gar Jal Certified Not Verified
6 Lalitpur Talbehat Sarsen 424537 Dhamna 137 137 100 Har Gar Jal Certified Not Verified
7 Lalitpur Talbehat Chobaro 424538 Chobaro 308 308 100 Har Gar Jal Certified Not Verified
8 Lalitpur Talbehat Chobaro 424539 Balarguwan 69 69 100 Har Gar Jal Certified Not Verified
9 Lalitpur Talbehat Bhuchera 424543 Chandro 241 241 100 Har Gar Jal Certified Verified
10 Lalitpur Talbehat Sunaura 424544 Sunaura 159 159 100 Har Gar Jal Certified Not Verified
11 Lalitpur Talbehat Sunaura 424545 Radhapur 164 164 100 Har Gar Jal Certified Not Verified
12 Lalitpur Talbehat Kadesra Bansi 424546 Kadesra Bansi 306 306 100 Har Gar Jal Certified Not Verified
13 Lalitpur Talbehat Kadesra Bansi 424547 Kadesra Khurd 147 147 100 Har Gar Jal Certified Not Verified
14 Lalitpur Talbehat Kadesra Bansi 424548 Hasguwan 141 141 100 Har Gar Jal Certified Not Verified
15 Lalitpur Talbehat Sunauri 424549 Sunauri 612 612 100 Har Gar Jal Certified Not Verified
16 Lalitpur Talbehat Piprai 424550 Piprai 289 289 100 Har Gar Jal Certified Not Verified
17 Lalitpur Talbehat Budaoni 424551 Budaoni 337 337 100 Har Gar Jal Certified Not Verified
18 Lalitpur Talbehat Budaoni 424552 Chandrapur 170 170 100 Har Gar Jal Certified Not Verified
19 Lalitpur Talbehat Udguwan 424553 Udguwan 135 135 100 Har Gar Jal Certified Not Verified
20 Lalitpur Talbehat Udguwan 424554 Banguwan Khurd 89 89 100 Har Gar Jal Certified Not Verified
21 Lalitpur Talbehat Udguwan 424555 Bhopalpura 48 48 100 Har Gar Jal Certified Not Verified
22 Lalitpur Talbehat Birdha 424557 Birdha 933 933 100 Har Gar Jal Certified Not Verified
23 Lalitpur Talbehat Gloragundera 424558 Gloragundera 725 725 100 Har Gar Jal Certified Not Verified
24 Lalitpur Talbehat Gloragundera 424559 Karokhat 13 13 100 Har Gar Jal Certified Not Verified
25 Lalitpur Talbehat Ugarpur 424560 Ugarpur 269 269 100 Har Gar Jal Certified Not Verified
26 Lalitpur Talbehat Ugarpur 424561 Bhesanwara Khurd 127 127 100 Har Gar Jal Certified Not Verified
27 Lalitpur Talbehat Ugarpur 424562 Bhesanwara Kalan 144 144 100 Har Gar Jal Certified Not Verified
28 Lalitpur Talbehat Rampur 424570 Rampur 441 441 100 Har Gar Jal Certified Not Verified
29 Lalitpur Talbehat Rampur 424571 Badanpur 52 52 100 Har Gar Jal Certified Not Verified
30 Lalitpur Talbehat Rampur 424572 Hansari 108 108 100 Har Gar Jal Certified Not Verified
31 Lalitpur Talbehat Udguwan 675188 VIDRA 150 150 100 Har Gar Jal Certified Not Verified

Scheme Progress

Villages Alloted Start Date of Trail Run Incoming Complaints Received Feedback from Gram Pradhan On Call ROAD DISMENTLING/RESTORATION(KM) Intake WTP T/W OHT CWR Distribution System INCL RWRM/CWRM (km) HGJ Status FHTC lectricity Comissioning of Village IMIS
All Complaints Close Complaints Pending Complaints All Complaints Close Complaints Pending Complaints Dismental(Filled by EE) Restored(Filled by EE) Restored %(Filled by EE) Villages where 100% road restoration completed(Filled by TPI) Restored(%) In progress(%) Functional Images/Videos In progress(%) Functional Images/Videos Required /completed (LAST WEEK ) Images/Videos Required Started Progress 0 to 25% Progress 26% to 50% Progress 51% to 75% Progress 76% to 99%
OHT completed
EE | Agency
OHT Fuctional(By ADM)
OHT with less manpower
EE | TPI
OHT and Signage Board Images/Videos OHT Logo Required Started Completed Completed
Required Laid Villages Alloted Household HGJ (100% Completed) HGJ Certified Villages FHTC Given as on Today FHTC Given as on Yesterday FHTC Given (last Week) FHTC % Connection Required/Completed Comissioned/Regular water supply(Verified by EE) Estimated Cost(Lacs) Estimated Cost(Lacs) Expenditure(%)
31 10-Jan-2024 15 11 4 10 10 0 23 23 100% 31 100% 100.00 Yes 0 / 0 100.00 Yes 1 / 0 0 / 0 0 / 0 8
+8
8
0 0 0 0 8 | 8 8 0 / 0 0 / 0 8 4
+0
4
4 4 157.92
+0.00
157.92
31 6972 31 31 6972 0 0 100.00 5 / 5 31 / 29 8836.00 7608.96 86.11%