Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Approve By Agency Status Approve By EE Status Automation Status
1 Sonbhadra Jain Const. 8175315 Kewatha GOV 11940.00 10327.61 Verified Verified view more

Scheme Assigne Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified Handed Over Villages
1 Sonbhadra Chopan Kharahra 479965 Kharara 1142 1142 100 Har Gar Jal Certified Not Verified
2 Sonbhadra Chopan Jugail 479966 Jogaeal 4123 4123 100 Har Gar Jal Not Certified Not Verified
3 Sonbhadra Chopan Tapoo 479967 Tapoo 468 468 100 Har Gar Jal Certified Not Verified
4 Sonbhadra Chopan Bharahri 479968 Bharari 927 927 100 Har Gar Jal Certified Not Verified
5 Sonbhadra Chopan Gothani 479979 Gothani 536 536 100 Har Gar Jal Certified Verified
6 Sonbhadra Chopan Gothani 479980 Gayghat 207 207 100 Har Gar Jal Certified Not Verified
7 Sonbhadra Chopan Ghatihta 479981 Ghatita 467 467 100 Har Gar Jal Certified Not Verified
8 Sonbhadra Chopan Ghatihta 479982 Mahrpur 91 91 100 Har Gar Jal Certified Not Verified
9 Sonbhadra Chopan Ghatihta 479983 Chandauli 122 122 100 Har Gar Jal Certified Not Verified
10 Sonbhadra Chopan Ghatihta 479984 Khewatha 192 192 100 Har Gar Jal Certified Not Verified
11 Sonbhadra Chopan Bardiya 479988 Bardiya 477 477 100 Har Gar Jal Certified Not Verified
12 Sonbhadra Chopan Tapoo 480052 Gosari 293 293 100 Har Gar Jal Certified Not Verified

Scheme Progress

Villages Alloted Start Date of Trail Run Incoming Complaints Received Feedback from Gram Pradhan On Call ROAD DISMENTLING/RESTORATION(KM) Intake WTP T/W OHT CWR Distribution System INCL RWRM/CWRM (km) HGJ Status FHTC lectricity Comissioning of Village IMIS
All Complaints Close Complaints Pending Complaints All Complaints Close Complaints Pending Complaints Dismental(Filled by EE) Restored(Filled by EE) Restored %(Filled by EE) Villages where 100% road restoration completed(Filled by TPI) Restored(%) In progress(%) Functional Images/Videos In progress(%) Functional Images/Videos Required /completed (LAST WEEK ) Images/Videos Required Started Progress 0 to 25% Progress 26% to 50% Progress 51% to 75% Progress 76% to 99%
OHT completed
EE | Agency
OHT Fuctional(By ADM)
OHT with less manpower
EE | TPI
OHT and Signage Board Images/Videos OHT Logo Required Started Completed Completed
Required Laid Villages Alloted Household HGJ (100% Completed) HGJ Certified Villages FHTC Given as on Today FHTC Given as on Yesterday FHTC Given (last Week) FHTC % Connection Required/Completed Comissioned/Regular water supply(Verified by EE) Estimated Cost(Lacs) Estimated Cost(Lacs) Expenditure(%)
12 01-Apr-2024 15 12 3 6 6 0 8 8 100% 12 100% 100.00 Yes 0 / 0 100.00 Yes 0 / 0 0 / 0 0 / 0 12
+0
12
0 0 0 0 12 | 12 12 0 / 0 0 / 0 7
+0
7
7 7 645.00
+0.00
645.00
12 9045 12 11 9045 0 0 100.00 8 / 8 12 / 12 11940.00 10327.61 86.50%